* rehosting day 3 |
Systems team visited the Ede BIT center to create backups and install a new drive. Systems are now passed over from old team of Philipp to the new team of Mendel and Wytze. The new team has a full book of work ahead of it and will be looking favourably on any locals who could help.
Root team has created trial keys but did not attempt a real root due to concerns over entropy and precise sub-root configuration. Current plan is to sort out these issues and re-convene end of November. This is not a blocking task.
At seven, the completion event took place at 'Planken Wambuis'. During a delicious dinner, the things happened in the last few days were spoken through and the things still to be done were mildly discussed. Around 22.30 the party broke up and went home.